در حال تکمیلDevelopmentHerat1 منابعبه‌روزرسانی: 2026-11-28 12:19:20🎙 رادیو را بشنوید

Construction work on the Herat section of the Turkmenistan-Afghanistan-Pakistan-India (TAPI) gas pipeline project has made significant progress, with approximately 92 percent of the work completed so far. According to available information, 142.9 kilometers of the total 150-kilometer pipeline planned across Afghan territory have been laid and welded, leaving only eight kilometers of pipeline to be […]

اطلاعات کوتاه

مکانHerat
موضوعDevelopment
منابع1
به‌روزرسانی2026-11-28 12:19:20

خط زمانی

  1. Ariananews

    Construction work on Herat section of TAPI project nears completion

منابع

Afghan sources

AriananewsPS
2026-11-28 16:46:32

Construction work on Herat section of TAPI project nears completion